Print Page FTP
Home Projects Safety Careers In the News Contact BE

HARBOR

Team BE started on limited notice with the most challenging area of Holcim – the harbor. They
were to construct one of the largest slack water harbors on the banks of the Mississippi River.
Over 1,800,000 cubic yards of material needed to be excavated and disposed of in spoils areas.
Approximately 900,000 cubic yards were excavated “dry” or conventionally. This was excavated
roughly 30 feet deep, utilizing large excavators and 40-ton articulated dump trucks. It was
disposed in two separate spoils areas, one of which created a large area for future laydown of
plant equipment and supplies.

The other 900,000 cubic yards was excavated “wet” or by dredging. This material was pumped by
dredge up to the dam site 1 1/2 miles away. The difference in elevation was approximately 200
feet. L.W. Matteson Company provided the dredging service. Depths ranged from 20 to 30 feet,
and consisted of silts, clays and sand.

In order to prevent sliding, protective rip-rap was anchored on the slopes. Special toe trenches
were dug 20 feet underwater and ranged from 4 to 15 feet deep and 12 to 40 feet wide. A
longreach excavator equipped with a GPS system was mounted on a portable spud barge to complete this part of the project accurately. Luhr Brothers provided and placed the rip-rap.
Massman Construction installed mooring cells to tie up barges, as well as sheet pile bulkhead for
a future barge loading/unloading facility. The cell construction, rip rap placement, bulkhead and
other finish work occurred at the same time, causing congested work areas on harbor waters.
However, effective management by Team BE allowed this area of the project to be completed
without incident.




"Unimin Corporation, a large industrial minerals producer and Bloomsdale Excavating have enjoyed a lengthy working relationship in the mining industry dating back to the late 1970's. Bloomsdale has been instrumental in supplying the equipment, employees and engineering expertise required to complete numerous overburden-stripping projects and in the construction of retention ponds for tailings storage. Bloomsdale's consistent commitment to the safety of their employees, the care of their equipment and the attention to detail during each of these recent projects has been instrumental in their ability to perform work for Unimin Corporation in the past, the present and in the future."
-Dan Rowe, Plant Manager
Unimin Corporation

RoadWay Site Development Overburden Removal Utilities
LevelTen Hit Counter 3.15
Last Modified 08/16/07 06:08    webmaster@blex.com